Construction (Design and Management) Regulations 1994:
The health and safety plan during the construction phase.
A quick phone call to Edocuments and we can prepare the plan almost as the phone
call is conducted.
The planning supervisor is responsible for ensuring that
the pre-tender stage health and safety plan is prepared.
This does not mean that the planning supervisor must
produce the plan directly, but the planning supervisor
must ensure that it is prepared.
The pre-tender stage health and safety plan is
essentially a collection of information about the
significant health and safety risks of the construction
project which the principal contractor will have to
manage during the construction phase.
Industry Standards - Health & Safety File
|
Edocuments Standard Health & Safety Plan complies with:
|
CDM - Construction (Design & Management) Regulations 1994
|
|
Managing Health and Safety In Construction ACoP, HSC, (HSG224)
|
|
|
Notes
The details for the Documentation in electronic
format section apply to the manuals.
For information about Edocuments standard service on how we collate the data and
create the documents click here.
|
|
Health and Safety Plan Template
|
Nature of the project (location, nature of
construction work, etc).
|
The existing environment (existing services,
surrounding land use, ground conditions, etc).
|
Existing drawings (available drawings of the
structure and the health and safety file if there is
one).
|
The design (information on the significant risks
which cannot be avoided).
|
Construction materials (health hazards from
construction materials which cannot be avoided).
|
Site-wide elements (positioning of site access or
egress points, location of unloading, layout and
storage areas, traffic routes, etc).
|
Overlap with the client’s undertaking (particularly
where construction work is to take place at the
client’s premises).
|
Site rules (could include emergency procedures,
permit-to-work rules, etc laid down by the client
when work takes place at the client’s premises).
|
Continuing liaison (procedures for dealing with
design work prepared for the construction phase).
|
|
|
For projects where a significant amount of design work
will be prepared as construction proceeds, specific
arrangements for dealing with this work may need to be
set out in the pre-tender stage health and safety plan.
This is important to ensure that the health and safety
aspects of the design work are considered and dealt
with properly by designers and the planning supervisor
during the construction phase. This will particularly
occur under the various design and build and
management contracting forms of procurement.
|
|
|
|